OEE for Multiple Parts – Single Machine (Multipart Processes)

How to Calculate OEE for Single Machine and Multiple Parts. Flexible manufacturing provides the advantage of producing many different parts on the same piece of equipment.  The same is true for processes such as stamping presses, molding machines, or machining operations. The first question

Posted in Advanced Lean Manufacturing, Availability, FREE Downloads, Lean, OEE: Overall Equipment Efficiency, Performance, Problem Solving, Quality, Quality Factor, Training Tagged with: , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

Weighted OEE: How To Calculate Total Plant OEE

In this post we will present a simple method to calculate a truly weighted OEE, including weighted factors Availability, Performance, and Quality. The QUICK weighted OEE method: Recalling our original definition of OEE, we are measuring how effectively our planned

Posted in Advanced Lean Manufacturing, Availability, Capacity, FREE Downloads, Lean, Lean Metrics, OEE: Overall Equipment Efficiency, Performance, Process Control and OEE, Quality, Quality Factor, Terminology, Training Tagged with: , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

OEE, Downtime, and TEEP

We have received several inquiries regarding equipment down time – periods of time when the machine is not scheduled to run.  We consider this to be scheduled down time or idle time and does not affect Overall Equipment Effectiveness (OEE),

Posted in Advanced Lean Manufacturing, Availability, Lean Metrics, OEE: Overall Equipment Efficiency, Performance, Process Control and OEE, Training, Uncategorized Tagged with: , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,
Sign Up and JOIN our TEAM

Make it Yours

Namecheap

Free Downloads

August 2017
S M T W T F S
« Sep    
 12345
6789101112
13141516171819
20212223242526
2728293031  

Categories

Archives

error: Content is protected !!