Lean Execution > Total Equipment Effectiveness Performance
Blog Archives

Lean Execution and OEE!

Welcome! If you are a first time visitor interested in getting started with Overall Equipment Effectiveness (OEE), click here to access our very first post “OEE – Overall Equipment Effectiveness“. We have presented many articles featuring OEE (Overall Equipment Effectiveness), Lean Thinking,

Posted in Advanced Lean Manufacturing, APQP, Availability, Capacity, Cost Control, Eliminate Waste, Execution, FREE Downloads, Lean, Lean Metrics, Lean Mindset, OEE: Overall Equipment Efficiency, Performance, Problem Solving, Process Control and OEE, Quality, Quality Factor, Root Cause Analysis, Terminology, Training, Trouble Shooting, Uncategorized Tagged with: , , , , , , , , , , , , , , , , , ,

How to Improve OEE – Any Questions?

Ask any Quality or Engineering manager and they will tell you that measurement systems are valuable tools to identify problems and opportunities.  The measurement system itself is not the answer – it is the data source, the EVIDENCE that drives the questions.  It is a

Posted in Advanced Lean Manufacturing, Availability, Capacity, Eliminate Waste, Lean Metrics, OEE: Overall Equipment Efficiency, Problem Solving, Process Control and OEE, Quality, Root Cause Analysis Tagged with: , , , , , , , , , , , ,

OEE and Morale

Is employee morale impacting your OEE?  If so, how much of a concern is it?  As we wrote in one of our recent posts,  “Perhaps the greatest “external” influence on current manufacturing operations is the rapid collapse of the automotive industry in the midst of our

Posted in Advanced Lean Manufacturing, Lean Metrics, OEE: Overall Equipment Efficiency, Process Control and OEE Tagged with: , , , , , , , , , , , ,

OEE Measurement Error

How many times have you, or someone you know, challenged the measurement process or method used to collect the data because the numbers just “don’t make sense” or “can’t be right”? It is imperative to have integrity in the data

Posted in Advanced Lean Manufacturing, Eliminate Waste, Lean Metrics, OEE: Overall Equipment Efficiency, Process Control and OEE Tagged with: , , , , , , , , , , , , , , , ,

OEE, Downtime, and TEEP

We have received several inquiries regarding equipment down time – periods of time when the machine is not scheduled to run.  We consider this to be scheduled down time or idle time and does not affect Overall Equipment Effectiveness (OEE),

Posted in Advanced Lean Manufacturing, Availability, Lean Metrics, OEE: Overall Equipment Efficiency, Performance, Process Control and OEE, Training, Uncategorized Tagged with: , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,
Sign Up and JOIN our TEAM

Make it Yours

Namecheap

Free Downloads

October 2017
S M T W T F S
« Sep    
1234567
891011121314
15161718192021
22232425262728
293031  

Categories

Archives

Twitter

error: Content is protected !!